Formwork Removal Time of Concrete Structures

The different concrete structures have different formwork removal times. In this article, we have covered the formwork removal time of the most common concrete structures used in the field of construction.

Formwork removal time is also called de-shuttering time.

formwork removal time
formwork for column

Formwork removal time of concrete structures

The formwork can be removed after the concrete is appropriately hardened into the mold. The mold should be steel or aluminum or wood. The formwork removal time of most common concrete structures is given in the below table.

Formwork TypeFormwork Removal Time
Wall Sides, Columns, and Vertical faces of the beam24 hours to 48 hours
Slabs (props left under)3-4 days
Beam soffits (props left under)7 days
Props Removal of Slabs:
i) Slabs spanning up to 4.5m14 days
ii) Slabs spanning over 4.5m14 days
Props Removal for beams and arches
i) Span up to 6m14 days
ii) Span over 6m21 days
Formwork Removal Time for different concrete structures

This formwork removal given in the above table is only for Ordinary Portland cement. OPC is the most common type of cement used for concrete structures.

Formwork removal time for other types of cement can be different due to their specific properties.

What is the best temperature for pouring concrete?

The suitable temperature to pour concrete varies between 38° to 58°F. Temperature is less than 38° can reduce the strength of concrete. Temperature more than 58° can lead to weakness, shrinkage, and cracking.